|
Patent
5,920,938 |
|
Failure
Mechanisms
Smith Point Bridge - Concrete Hinge Bearing Pad Replacement Demonstration By : Stanley E. Elcock, P.E. and Stanley D. Elcock
|
|
Smith Point Bridge is a 9 span, 1424 foot long structure located in Humboldt County 5 miles south of Garberville, California on US Highway 101. Built in 1980, it is two conventionally reinforced 2 cell concrete box girder bridges with common pier walls. There are two hinges per separated superstructure for a total of four hinges. The bridge has some unique features; however, it has the common problem of early failed hinge elastomeric bearing pads. These elastomeric bearing pads allow the bridge to expand and contract with temperature changes and prevent concrete-to concrete bearing. Within 2 years after construction the bearing pads permanently compressed over 1" at the south hinges and 1" at the north hinges. Caltrans bridge reports noted and monitored the problem, concluding that the bearing pads had stabilized without any further evidence of continued bearing pad compression by 1991. In June of 1996 Smith Point Bridge was 1 of 4 bridges to be retrofitted under a $565,000.00 Seismic Retrofit contract. The retrofit strategy for the Smith Point Bridge included pipe restrainers and bolsters at the hinges, but excluded bearing pad replacement due to excessive cost estimated at an additional $400,000.00. |
|
|
As part of the new retrofit
work, 8- 5/8" diameter pipe restrainers were planned to be inserted
in 9" diameter cored holes through the hinges. There were two pipe restrainers per box girder cell for a
total of 16 pipe restrainers. One end of the pipe restrainer was planned
to be cast in a newly constructed bolster, while the opposite end extended
10" beyond another newly constructed bolster.
Early in the construction the problem of replacing the hinge
bearing pads was once again addressed.
The CALTRANS Office of Structure Design relayed the past
considerations during the retrofit strategy and the rationale ( an
additional cost of $400,000.00 for bearing pad replacement and the bearing
pad compression had stabilized ) for excluding bearing pad replacement
from this retrofit project.
I had reviewed the as-builts
at the beginning of the project and determined that the hinges were
bearing concrete-on-concrete and that it appeared that the south hinge
shear keys were crushed. The
Standard Drawing in the as-builts only required 1" of expanded
polystyrene on top of the concrete shear keys.
This accounted for the "stabilized compression".
Crushed shear keys would account for the compression over 1". This fact, although obvious today, had been overlooked until
now.
Seismic
Retrofit Hindsight - the BIG mistake For
the complete article, licensing information,
and how our patent can help you, please e-mail: elcock@northcoast.com
|